Best value procurement in the construction industry
Contents |
[edit] Introduction
The best value procurement (BVP) approach is a method of purchasing construction works, services and so on. It considers criteria, such as quality, reliability and expertise, rather than just price to assess value.
[edit] History
This method was developed by the Performance Based Studies Research Group (PBSRG) in the United States (where it is most commonly used). It is also practised in the United Kingdom and the Netherlands, where it is referred to as ‘prestatie inkoop’ or performance procurement.
[edit] BVP or MEAT?
The idea behind best value procurement is to compare the long term costs and benefits associated with the vendor selection process. It is similar to the Most Economically Advantageous Tender (MEAT) principle, and both use assessment criteria such as:
- Quality.
- Price or cost using a cost-effectiveness approach.
- Technical merit.
- Aesthetic and functional characteristics.
- Accessibility.
- Social characteristics.
- Environmental characteristics.
- Innovative characteristics.
- After-sales service and technical assistance.
- Delivery conditions such as date, process and period.
In addition to MEAT criteria, best value procurement also assesses the potential for eliminating (or minimising) risk, so procurement decisions are made based on predictability. Best value procurement assigns weightings to each criteria - including reliability- and vendors or contractors are scored on each. Decisions are based on the final tally.
[edit] The process
There are four phases of the best value procurement process::
- Preparation.
- Selection.
- Clarification.
- Execution.
Being data driven, best value procurement simplifies the decision making process. This minimises the influence of vendors in the procurement process and maximises the power of the procurer.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.